This week Atlas Paving Company began the process of resurfacing three miles of Broadway from Waterloo to Simpson Road. As of Friday, May 17, the project was complete.
Another improvement on the roadway will be the application of new safety striping. ODOT conducted a bid letting for the striping on Thursday, May 16 and will award the bid June 3. According to ODOT, low bidder was Action Safety Supply at $27,752.30. The bid cost included
safety striping not only for Broadway but for multiple areas of roadway within District 1.
The new paving and striping will tie into a previous 2 1/2 mile asphalt overlay on Broadway which was completed in 2010. That project began at Simpson and ended one-half mile south of Seward Road.
Another project near completion is the new bridge on Charter Oak Road west of Santa Fe. Contractors finished pouring traffic rail last week and are now turning their attention to the roadway. There are still culverts, rip rap and sod to install, as well as guardrail, but we
anticipate the bridge opening to the public soon.