Broadway paving complete; striping to follow

Bookmark and Share

This week Atlas Paving Company began the process of resurfacing three miles of Broadway from Waterloo to Simpson Road. As of Friday, May 17, the project was complete.

Mark SharptonAnother improvement on the roadway will be the application of new safety striping. ODOT conducted a bid letting for the striping on Thursday, May 16 and will award the bid June 3. According to ODOT, low bidder was Action Safety Supply at $27,752.30. The bid cost included
safety striping not only for Broadway but for multiple areas of roadway within District 1.

The new paving and striping will tie into a previous 2 1/2 mile asphalt overlay on Broadway which was completed in 2010. That project began at Simpson and ended one-half mile south of Seward Road.

Another project near completion is the new bridge on Charter Oak Road west of Santa Fe. Contractors finished pouring traffic rail last week and are now turning their attention to the roadway. There are still culverts, rip rap and sod to install, as well as guardrail, but we
anticipate the bridge opening to the public soon.

For more information about District 1 activities, go to www.commissiondistrict1.com

TOP POSTS

Be the first to comment on "Broadway paving complete; striping to follow"

Leave a comment

Your email address will not be published.


*


This site uses Akismet to reduce spam. Learn how your comment data is processed.